Huoshenshan received the first batch of patients, and huoshenshan hospital began to treat the first

According to CCTV news, after the army's support for the Hubei medical team's meticulous and orderly preparations, the Wuhan fire god hill hospital today formally began to receive the confirmed diagnosis of New Coronavirus's pneumonia, and was admitted to the first batch of patients today (February 4th) at 9 o'clock.

According to voice of China, 1400 medical and nursing personnel from the whole army were stationed in New Coronavirus, Wuhan, mount New Coronavirus, after infection with pneumonia specialist hospital. They immediately prepared medical materials, infection control, rules and regulations, and so on.

At 9:26 on the 4th, huoshenshan hospital began to treat the first batch of 50 patients from three hospitals, including Wuchang hospital and Hankou hospital. The transfer task is in the charge of Wuhan emergency center, and the ten emergency vehicles are all ambulances.

Huoshenshan hospital construction timeline

Building a hospital in ten days is an "impossible task" in the eyes of many people.

According to Xinhua news agency, Fang Xiang, project manager of the third company of China Construction Third Engineering Bureau, has been engaged in the civil construction industry for many years. He said: 'according to the conventional process, projects with a construction volume of more than 30000 square meters will take at least two years. In a state of emergency, it takes one month to build temporary buildings, not to mention a new infectious disease hospital. "

Unlike the Xiaotangshan Hospital built in seven days during SARS, the construction of huoshenshan hospital coincided with the return of a large number of workers during the Spring Festival holiday, 'not to mention raw material procurement and logistics transportation, even eating, drinking and Lasa on the construction site, these logistics are difficult to guarantee'. A staff member of Wuhan Urban Construction Bureau introduced.

The epidemic situation is not waiting. Under the severe situation, on the day of new year's Eve, the construction party has leveled 50000 square meters of all sites, equivalent to the size of seven football fields. 150000 cubic meters of excavated earth is enough to fill 57 standard swimming pools. On the first day of the lunar new year, all workers and machines rotate day and night without any slack. At the peak, more than 7000 workers, more than 800 excavators, bulldozers and other equipment operate at the same time.

A short time axis, recording how the fire god mountain hospital grew in the world's attention--

· On January 23, relevant parties decided to build a special hospital with reference to the "Xiaotangshan model";

· On January 24, the relevant design scheme was completed, and hundreds of excavators began to level the land;

· The project was officially started on January 25;

· On January 26, the first model house was completed;

· On January 27, the first batch of container plank houses were hoisted and erected;

· On January 28, the steel structure of the double-layer ward area began to take shape;

· On January 29, the framework installation of more than 300 box type plank houses was completed; Electromechanical pipeline operation shall be carried out simultaneously;

· On January 30, the laying of impervious membrane was fully completed; Equipment hoisting in sewage treatment room shall be carried out simultaneously;

· On January 31, 90% of the containers were assembled; Installation of movable plank house skeleton: 3000m2;

· On February 1, the installation of medical supporting equipment was fully launched;

· On February 2, the hospital was completed and delivered.